3 Marla House Construction Cost & Details

3 Marla House Construction Cost in Pakistan (2024)

ItemQuantityCost Range (PKR)
Bricks20,000 to 30,000100,000 – 180,000
Ravi Sand30,000 – 40,000
Chenab Sand20,000 – 30,000
Margala Crush55,000 – 65,000
Sargodha Crush40,000 – 60,000
Cement (400 bags)480,200
Steel (1 ton)1,000 kg380,000
Electrical Wiring508,690
Safety Grills50,000
Steel Choughat90,000 – 150,000
Flooring TilesVaries
Decorative Paint50,000 – 100,000
Ceilings (False/POP)120 – 250/sq ft
Wooden Work & Main Gate150,000 – 300,000
Kitchen Accessories200,000 – 400,000
Bathroom Fittings220,000 – 480,000
Electrical Equipment1,000 – 100,000
Stair Railings500 – 1,500/ft
Mirrors, Windows, Doors200,000 – 300,000

Comprehensive Guide to 3 Marla House Construction

Constructing a house on a 3-Marla plot can vary significantly based on location, materials, and design complexity. Whether you’re aiming for an economical build or a premium finish, understanding the costs involved is crucial.

Covered Area of a 3 Marla House

A 3-Marla plot typically covers approximately 816.524 square feet (69.523 square meters). The covered area is crucial in determining the number of rooms, floors, and overall space utilization. The design of the house also significantly impacts the construction cost, with intricate designs being more expensive than simpler layouts.

Grey Structure Cost Breakdown

The grey structure includes foundational work, wall construction, plumbing, electrical wiring, floor leveling, and wall plastering. For a 3-Marla house, the essential materials include bricks, sand, crushed stone, cement, and steel, along with the costs of labor and other services.

  • Bricks: Approximately 20,000 to 30,000 bricks are required, costing between PKR 100,000 to PKR 180,000.
  • Sand: Both Ravi and Chenab sands are used for concrete and plaster. Ravi Sand costs between PKR 30,000 to PKR 40,000, while Chenab Sand costs between PKR 20,000 to PKR 30,000.
  • Crushed Stone: Margala Crush costs around PKR 55,000 to PKR 65,000, and Sargodha Crush costs around PKR 40,000 to PKR 60,000.
  • Cement: Approximately 400 bags are needed, with a total cost of PKR 480,200.
  • Steel: About 1 ton is required, costing approximately PKR 380,000.
  • Electrical Wiring: Essential for setting up a safe electrical system, costing around PKR 508,690.

Essential Construction Materials

Additional construction materials like safety grills, steel choughat, flooring tiles, and paint play a crucial role in the house’s overall look and durability. Costs vary based on quality and design, with options available for various budget levels.

Detailed Cost Analysis

From flooring to ceilings, woodwork, and kitchen/bathroom accessories, every detail adds up to the overall cost. For instance, flooring tiles and decorative paint add to the aesthetic appeal, while sturdy stair railings and wooden work enhance the house’s functionality and durability.

Additional Costs and Considerations

Labor costs, design fees, and miscellaneous expenses should also be factored in. These can include unforeseen costs such as delays, material wastage, or design changes.

Conclusion

Constructing a 3-Marla house in Pakistan requires careful planning and budget management. The total cost can vary based on your choices of materials, labor, and design. This guide provides a detailed breakdown of the costs, helping you make informed decisions to ensure your project stays within budget while meeting your expectations.